DCSIMG

M62 resurfacing work between Rishworth and Outlane

M62

M62

The Highways Agency will begin work to resurface stretches of the M62 between J22 (Rishworth Moor) and J23 (Outlane) from Monday.(17th)

The work will take place overnight on both the eastbound and westbound carriageways, and is due to be completed by March 21.

It will be necessary to carry out lane closures on the M62 main carriageways and on the slip roads at junction 22.

The closures will take place from 8pm each evening until 6am the following morning.

When the J22 eastbound entry slip road and westbound exit are closed, a clearly signed diversion to M62 junction 21 and back to junction 22 will be in place. Only one slip road will be closed at a time.

 
 
 