First phase of work to revamp Calderdale town centre ‘on target’
Contractors are on schedule to complete the first phase of the multi-million pound regeneration of a Calderdale town.
Esh Construction are working on a phased scheme to improve Brighouse town centre, using funding from Brighouse’s £19.1m Town Deal award.
Responding to questions from Brighouse traders, Esh said that phase one – focusing on the west area of the town, taking in Commercial Street between Gooder Street and Park Street, Briggate between Thornton Square and Commercial Street, and Market Street, West Park Street and Ship Street – is on target to be completed by the end of July.
Esh said: “To complete our work in the safest and most efficient way possible, it’s essential we follow a strict programme and ensure we complete work on phase one before we move onto the next.


“We’re on target to complete phase one at the end of July 2026 and immediately move onto phase two.”
Issues which can affect timescales include delivery of materials, inspections being conducted and the weather, says the contractor.
Updates will be more precise as the date nears.
Phase two sees attention switch to the east, taking in Commercial Street between Park Street and Bradford Road, and Park Street, Park Row, King Street and Bradford Road, with work scheduled to go into the winter.
Esh said they recognised the importance of the Christmas period for traders and the phase two works were scheduled to run until early December.
Access for deliveries to affected businesses will be maintained throughout the second phase, as it did in the first, says Esh.
The third phase concentrates on the Bethel Street area, including Bethel Street car park. At the moment, this is scheduled from winter 2026 to spring 2027, completing within the 18-month estimated timespan.
Esh also said there may be a way in which businesses who say they have suffered financial loss from the regeneration work can claim some money back.
They said local authorities are not liable to pay compensation for loss of trade that might arise from highway improvement or maintenance works which are undertaken in the course of their statutory duties.
But Esh, with Calderdale Council, are looking into a way some businesses might be able to receive some relief on their business rates, if they have to pay these, said the contractor.
Meantime, one trader wanted to know what was happening to Yorkshire stone which has been dug up as part of the project.
Esh said stone which had been dug up in the first phase of the three-phase scheme would be reused at the next stage.
“We’re reusing the stone dug up so far, and some other from across the district, for phase two of the works,” they said.