Plans to site an approximately ten tonne air source heat pump on top of the roof of a Calderdale school have been submitted.

The roof is above a staff room at Ryburn Valley High School, on St Peter’s Avenue in Sowerby, according to one report, by acoustic consultants Sharps Redmore, submitted with the papers.

If permission is given to MITIE Technical Facilities Management Ltd’s planning application by Calderdale Council, the pump will be supported by a new steel platform.

The application is for the pump and acoustic and visual screening.

Ryburn Valley High Schoolplaceholder image
Ryburn Valley High School

The new heat pump will greatly reduce by around two thirds the school’s carbon footprint, according to supporting papers.

The papers say 90.6 per cent of heat demand met by low-carbon technology, representing “a significant improvement over the existing gas system and aligns with climate policy objectives”.

A structural assessment report, which forms part of supporting documents with the application, says the proposals include installation of a new air source heat pump with a weight of approximately ten tonnes on the existing flat roof structure.

Additionally, the air source heat pump will be supplemented with installation of buffer vessels – water tanks – within an existing second floor plant area.

According to the assessment prepared for MITIE, steel members in the existing structure have spare capacity to accommodate some additional load.

And structurally, a new steel platform is to be provided above the existing roof line, connected to the existing structure.

It will allow the air source heat pump load to not be supported by the existing roof beams, and also provides some acoustic and vibration separation.

There will also be acoustic and visual screening to deal with visual and sound impacts from the new system.

Some existing plant equipment on the roof will be moved to accommodate the new kit, according to the papers.

The internal second floor service zone slab support structure has sufficient capacity for the support of new water tank and buffer vessels, according to the reports.

If more flexibility is required, if specifications change, a new steel platform can be installed to sit above this slab level.