How Environment Agency plans to beat flooding in Elland and Sowerby Bridge
An alleviation scheme to better protect more than 60 properties in Elland needs to tackle both surface water and off-hillside flooding, councillors have heard.
Twenty-six properties were badly hit by December 2015 flooding and 35 homes were hit when Storm Ciara impacts struck the Park Road area of town in February 2020, Calderdale Flood Recovery and Resilience Programme Board heard.
Environment Agency officers said the project was at the stage of reviewing the economics, gathering data and developing a strategic outline business case for work.
The surface water option is viable from partnership funding and available grant and work to address surface water flooding is now being undertaken with Calderdale Council.


Close to the Calder and Hebble Navigation and River Calder, work will continue to find technical solutions producing economic benefit for fluvial aspects, said agency officers.
This included working with the council and the Canal and River Trust, they said.
It was hoped a single stage business case could be worked up within the next 12 months with an aim of delivering solutions as soon as possible.
Other protection schemes at an early stage of development were presented to the board.
An outline business case is being prepared for Sowerby Bridge, which has seen much worsened flooding in recent years.
The aim in Sowerby Bridge is to better protect 46 homes and more than 40 commercial properties, from flooding including from the River Calder and the River Ryburn.
Surveying, baseline and hydrology work has been completed and is being reviewed by the agency.
Once modelling is agreed, then different options available will be looked at, board members heard.
There are many constraints including funding, limited benefits and particularly a number of listed structures which make the project a tough one, said officers.
“It is a really challenging project because it is heavily constrained, for example by listed structures,” one said.
Although a scheme at Callis Bridge, between Hebden Bridge and Todmorden, was completed on the River Calder two decades ago, the aim was to look at an option covering all kinds of flood risk.
Leader of Calderdale Council, Coun Jane Scullion (Lab, Luddenden Foot) said Callis had long been seen as “the canary in the coalmine” when it came to flooding in Calderdale, signalling when issues were serious.