Hundreds of Mytholmoryd home protected as parts of £35m flood defences are completed

Five new areas of the £35m flood defences in the Upper Calder Valley are now complete with the whole scheme expected to be finished by the end of the year.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

These are the areas of the Mytholmroyd Flood Alleviation scheme, which will help better protect almost 400 homes and businesses from flooding, that have been completed.

Greenhill Industrial Estate - new flood defence walls with an access ramp have been installed alongside Vale Upholstery’s building. Two new flood gates have also been put in place at either side of the private access bridge over the River Calder along with flap valves to help drain water away quickly if the defences do overtop.

Hide Ad
Hide Ad

St Michael’s Church - new flood defence walls including glass panels are completed next to and opposite the church and the river channel has been widened (up to 8m). Viewing platform and benches have been installed at the site of the former post office and the area is now open to the public, landscaped with trees and shrubs. The tennis courts have also been re-instated.

Paul Swales, senior advisor for the Environment Agency with Calderdale Councils Cabinet Member for Climate Change & Resilience Cllr Scott Patient and Chris Blenkarn VBA project manager.....Paul Swales, senior advisor for the Environment Agency with Calderdale Councils Cabinet Member for Climate Change & Resilience Cllr Scott Patient and Chris Blenkarn VBA project manager.....
Paul Swales, senior advisor for the Environment Agency with Calderdale Councils Cabinet Member for Climate Change & Resilience Cllr Scott Patient and Chris Blenkarn VBA project manager.....

River Calder and Cragg Brook Confluence - New flood walls in the gardens of Streamside Fold are complete - some of them are already beginning to change colour and blend into the local environment. Some glass panels and flap valves have been installed on the left and right banks of the River Calder. The repairs to the confluence wall following the movement of the existing structure during the February flooding is now finished with all temporary works removed from the channel.

Caldene Bridge - A major milestone for the scheme was achieved on May 18 when the new bridge opened to motorists and pedestrians. This was carried out during the height of the coronavirus pandemic and measures were taken to make sure all work was carried out in line with government and industry guidance for safe working. Demolition of the old Caldene Bridge, which was a major constriction to river flow, began on May 26 and the final lifting out of the bridge beams took place on June 19 2020. Excavation works have been carried out to widen this section of the river and wall construction is ongoing. The area beneath the new bridge is nearly twice the size of the old bridge and the new two span bridge is 13m wider than the old Caldene Bridge which will help better protect homes and businesses from the risk of flooding in the future

White Lee Clough – A new overflow has been created from White Lee Clough culvert beneath Midgley Road to divert water away from Mytholmroyd into the Rochdale Canal. This area has been landscaped with trees, plants, shrubs, hedges and grass seeded.

Hide Ad
Hide Ad

Brearley Fields Canal Spillway - a new canal spillway has been installed to re-connect the Rochdale Canal canal flood waters with the River Calder. The canal towpath has re-opened with a new footbridge over the concrete spillway.The embankment has been re-graded with erosion protection beneath. A new footpath at the base of the embankment has been installed as part of the Calderdale Council’s Brearley Fields Wetland Nature Reserve.

Luddenden Foot – new walls, ramps and steps have been constructed in the gardens of properties and the bowling club. Reinstatement of the gardens and the road repairs are finished. Property flood resilience work will also be carried out to some of the properties.

The flood defences have been developed by the Environment Agency in partnership with Calderdale Council. Design and construction of the scheme is being carried out by main contractor VBA, a joint venture comprising VolkerStevin, Boskalis Westminster and SNC-Lavalin’s Atkins business.

Paul Swales, senior advisor for the Environment Agency, said: “The coronavirus pandemic has had an impact on the construction of Mytholmroyd flood defences, however, the project team has worked hard to continue to make progress, whilst adhering to Government guidelines for safe working.

Hide Ad
Hide Ad

“We now expect the flood defences to be completed towards the end of this calendar year, however this is still dependant on favourable weather conditions and provided that no other unexpected circumstances arise.

“Our team is working with the Department for Education to look at installing flood resilience measures to Burnley Road Academy which will be in addition to the flood defence works. This is a key asset for the village and will help reduce risk further to school children, parents and teachers from future flooding.”

During the next few months, wall construction will continue at Brearley upstream and downstream of the bridge - this work had to be paused following the discovery of an additional arch on the listed structure. Planning permission has just been given to carry out work in the area near Scar Bottom Cottages and so vegetation clearance, wall construction and surveys for property flood resilience have got underway.

Calderdale Council’s Cabinet Member for Climate Change & Resilience Councillor Scott Patient, said: “It’s great to see that so much progress has been made with building these flood defences which will play a vital part in providing better protection for the Mytholmroyd community.

Hide Ad
Hide Ad

“I would like to thank local residents, businesses and commuters for their patience during the inevitable disruption caused to the village whilst this major and complex construction work is being carried out.”

Comment Guidelines

National World encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.