Looking back one year on from reopening of Elland Bridge

It's almost a year since Elland Bridge reopened to traffic '“ a milestone in Calderdale's recovery from the Boxing Day floods.
Elland Bridge reopened last year after over 12 months of workElland Bridge reopened last year after over 12 months of work
Elland Bridge reopened last year after over 12 months of work

The devastating floods caused damage to homes, businesses and schools as well as many roads and bridges which were badly damaged or destroyed

Over the last two years, 16 bridges that were damaged during the flooding have reopened. One of the most eagerly awaited events was the reopening of Elland Bridge, which opened to traffic in February 2017.

Hide Ad
Hide Ad

Calderdale Council worked with the Canal and River Trust to start the process of rebuilding Elland Bridge and steps were taken to keep the community connected with temporary footbridges in place throughout.

Rebuilding the 1811, Grade II listed bridge was a very complex and careful process. For example, 28 major utility cables and pipes had to be redirected and to preserve the historic features, all of the original stone has been reused on the new bridge.

The work was financed through the Department for Transport flood recovery fund with £5.5 million financing the rebuild of Elland Bridge and the nearby Crowther Bridge, which also reopened last year.

Calderdale Council’s Cabinet Member for Regeneration and Economic Development, Coun Barry Collins, said: “The damage caused by the floods was devastating for the whole of Calderdale, but the closure of Elland Bridge had an especial impact on the town of Elland.

Hide Ad
Hide Ad

“Reopening this bridge was a really important event for the borough and almost a year on we’re delighted that communities are once again connected.

“This major route into Elland is being well used by cars and pedestrians and the tow path and canal is back open for boaters, canoeists, cyclists and walkers to enjoy.”

Other significant works throughout 2017 included:

· Repairs and reopening of Crowther Bridge, Cromwell Bottom

· Repairs and reopening of Wilson Bridge, Copley

· Damage repairs to Elland River Bridge

· Repairs to a damaged wall on Huddersfield Road Bridge, Brighouse

· Repair work to River Street Bridge, Hebden Bridge

Hide Ad
Hide Ad

· Repairs to highway and wall at Stoodley Glen River Bridge, Eastwood

· Repairs to damaged parapet on Stubbing River Bridge and major repairs to grade ll listed structure, Stubbing Canal Bridge, near Hebden Bridge

· Replacement footbridge, Shibden Park, Shibden

· Replacement of damaged parapets on Playing Fields footbridge, Sowerby Bridge

· Damage repairs to Shaw Wood Road Bridge, Todmorden

· Landslip highway repairs and new retaining wall A646 Falling Royd, Mytholmroyd

· Major land stabilisation works at Scout Road, Mytholmroyd

Since the floods, assessments have taken place on 344 highway structures and staff cleared debris from all structures along the River Calder and Calderdale canals.