When will Halifax's new pool be ready: Demolition work in full swing to prepare for construction of town's new leisure centre and pool
Parts of the old Halifax Leisure Centre have been demolished to prepare for construction of the town’s new facility.
Work finally started on the site in September, with North Bridge car park closed until the new leisure centre is finished.
Halifax has been without a swimming pool since 2020 and without its leisure centre since 2022.
The plan to build a new combined pool and leisure centre was on hold for a year when inflation costs spiralled.


It has since been restarted with some cuts to what was planned and the estimated completion date for the new facility is now 2027.
The demolition process involves stripping out internal fixtures and fittings, then using excavators and demolition equipment to reduce the building structure to ground level and remove the foundations.
As part of a sustainable approach to materials and construction, masonry and concrete from the demolition of the old buildings will be repurposed and processed on-site to be reused in the new leisure centre construction, and the old sports hall is being retained and refurbished.
The new Halifax Leisure Centre will include a 120-station fitness suite, three multi-function studios and a dedicated spinning studio, an eight-court sports hall, a 25 metre six-lane swimming pool with spectator seating, and a learner pool with a viewing and seating area, a changing places facility, wellbeing spaces, a soft play and adventure area for children, and a café and community area.


Councillor Jane Scullion, Leader of Calderdale Council, said: “It’s great to see this latest milestone progressing. It’s the end of an era as we say goodbye to the old leisure centre and move with excitement towards a new top-class sports, health and wellbeing facility for everyone in our communities, complementing our existing borough-wide facilities.
“It’s another example of the unprecedented investment underway across Halifax and Calderdale to support thriving towns and places for people and businesses.”
William Kay, Regional Director for Yorkshire and the North East at contractor Tilbury Douglas, said: “As this project moves into its next phase, our focus remains on creating a facility that genuinely enhances the wellbeing of people across Calderdale. Working closely with the Council, we’re shaping a space that supports healthier lifestyles, brings communities together and provides opportunities for future generations. This is an important investment in Halifax, and we’re committed to delivering a sustainable, high quality centre that reflects the needs and aspirations of the borough’s residents.”