Contractors give statement after Brighouse town centre revamp pause
The firm contracted to carry out a regeneration scheme in Brighouse has provided a statement about Calderdale Council’s decision to pause the work.
The Courier asked Esh Construction whether halting the project would incur any financial penalties.
Steven Garrigan, divisional director at Esh Construction, responded: “We are working closely with our client, Calderdale Council, to understand and support with any next steps following the announcement about the wider scheme.
"In the meantime, our focus remains on the safe and successful delivery of Phase 1, which is scheduled to continue through to August.”


The Courier has requested more details from Calderdale Council, including an estimation of how long the work would be paused for and whether it will mean the project will end up costing more.
That information has not been provided but Councillor Daniel Sutherland, leader of Calderdale Reform and the council, has made a statement.
In it, he said: “It is difficult to change a scheme that is currently underway, but we believe the seriousness of this case merits a pause whilst a review can be undertaken.”
Calderdale Reform – which now runs the council – announced on its Facebook page last week that regeneration work in Brighouse would be halted once the first phase is done later this summer while the councillors develop a redesigned scheme “that works better for business owners, shoppers and the town as a whole”.
The news has been welcomed by some businesses in Brighouse town centre who had contacted councillors, worried about the impact the work was having on footfall and trade.
But concerns have also been raised by Courier readers about how long a pause will delay the work’s completion, and about leaving the town with work “half done”.
Former Calderdale councillor George Robinson, who was a Conservative councillor representing the Hipperholme and Lightcliffe war for nine years, has written to Coun Sutherland urging him to reverse the pause.
To help traders, he says completing the work as planned would be a better option alongside suspending parking charges and launching a campaign urging people to shop in Brighouse.
The Brighouse town centre work is being funded by Government Town Deal cash.
Work got underway in January and was expected to take 18 months.
Phase one – which is almost complete – has been on Commercial Street between Gooder Street and Park Street; Briggate between Thornton Square and Commercial Street; Market Street; West Park Street and Ship Street.
Phase two was to see work done on Commercial Street between Park Street and Bradford Road; Park Street; Park Row; King Street and Bradford Road).
Phase three was planned in the Bethel Street area, including Bethel Street car park.
Footways are being widened, new pedestrian areas are being created on Commercial Street and Bethel Street, and a new public space will be made in Thornton Square to host community events.