Halifax Courier readers react to plans to pause Brighouse town centre works

Halifax Courier readers have reacted to plans to pause the major redevelopment project in Brighouse town centre.

Yesterday (Thursday) The Reform group in charge of Calderdale Council announced it would pause further town centre work in Brighouse while a revised scheme is developed.

The work, which is part of the £19.1million Brighouse Town Deal Project, has been taking place since January this year and was expected to take 18 months.

placeholder image
Read More
Next phase of town centre development work in Brighouse paused
The works in Brighouse town centre.placeholder image
The works in Brighouse town centre.

Phase one of the project is due to finish this summer, followed by another two phases that were expected to last around six months each.

After a backlash from some town centre business owners about the impact they say the work is having on trade, the Reform group has said any work yet to take place will be paused.

Some readers have welcomed the news.

Daniel Hoyle shared: “Good! We’ve wasted far too much money and now they’re doing it again and spoiling a perfectly good little town.”

Good,” said Liz Austin. “Yes work was required to road surfaces and to smarten the place up, but these works were not. Total waste of tax payers money. I'm glad they are also reviewing planned cycle lanes.

"It made absolutely no sense to have cycle lanes running down from Bailiff Bridge to Brighouse as well as creating one, running parallel on the old train line. Now they need to stop the crazy works between piece hall and the train station before they get too far.”

Lorraine Hoyle said: “Good news! Have people who disagree seen what pedestrianisation has done to Elland. People go to the smaller towns because it's easy to park and flat. People with mobility problems prefer it. Not all people who have such issues are awarded blue badges.”

While some readers are pleased with the announcement others feel that the work was benefitting the town.

Patrick Bodger said: “Shopping in Brighouse is like a video game trying to dodge the cars. This could have improved it.”

Ash Ad shared: “The town centre would have been lovely and pedestrianised making it far more appealing for people to come and visit. A transformation the town has needed for years. Parking would need looking at of course but the works ongoing were starting to look really nice with more trees and walkways without the hazard of cars.

“I hope this isn’t just going to sit there unfinished because this will cause far more damage to the town than if it was just completed in the first place. It isn’t just the cycle lanes, it’s the bigger picture of giving the town the makeover it’s needed for decades.”

“I'm not really sure what they mean,” said Richard Langford. “Will this mean work stops and Brighouse is left looking like a dump for several years while someone decides what happens next? People are trying their best to support business and use Brighouse and will do so over the 18m period the works were planned for. Extend that out to 5 years and people just won’t put up with it. They will stay away. Brighouse is hard work at the moment, once its finished it won’t be. Why extend the pain? Why not try and make things happen quicker?”