Major Calderdale bridge damaged by storms to remain shut until July

A major bridge into a Calderdale town centre will remain closed into July.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

Following the completion of survey work, repairs will soon take place to a Brighouse bridge which was badly damaged by Storm Ciara.

Rastrick Bridge in Brighouse has been closed to traffic since late April, after diving surveys identified some scour holes under one of the central pillars and some hairline cracking to one of the bridge arches.

Hide Ad
Hide Ad

A contractor has now been appointed to carry out the complex repair work, which will involve pumping concrete support into the holes and then installing boulders around the structure to add further protection.

Rastrick Bridge back in Brighouse 2015. Picture by Mark Minas Copyright: otherRastrick Bridge back in Brighouse 2015. Picture by Mark Minas Copyright: other
Rastrick Bridge back in Brighouse 2015. Picture by Mark Minas Copyright: other

Calderdale Council’s Cabinet Member for Regeneration and Resources, Councillor Jane Scullion, said: “In February this year, Storm Ciara caused millions of pounds worth of damage to infrastructure in Calderdale.

“Although so much has happened since, with the outbreak of COVID-19, we’ve continued to work hard to assess the damage and put in place a programme of repairs.

“Much of the damage to our roads and bridges has been of a complex nature, which has required specialist repairs. I’m pleased that despite the challenges associated with coronavirus, we’ve been able to appoint the relevant experts to begin work to repair Rastrick Bridge.

Hide Ad
Hide Ad

“We know the road closures around the Brighouse area have caused disruption for those still needing to travel and we apologise for this inconvenience. We’re doing all we can to complete the work as quickly as possible and are also putting in place measures to prevent the potential for further problems in the future.”

Work will commence on Monday June 22 to place the concrete under the pier.

The bridge will reopen to traffic when this work is complete, however the work is very weather dependent and any heavy rainfall could delay the completion said the Council.

The boulder work can be done whilst the road is open and weather permitting, the work should be fully finished before the end of July, with the bridge being opened to traffic in mid-July.