Traders 'just need some help' from council amid Calderdale town centre revamp
Traders worried about falling footfall amid major regeneration work in their Calderdale town say they need more council help to get them through the work.
The first stage of the £19.1m Town Deal-funded regeneration work in Brighouse is expected to finish later this summer.
But Calderdale Council’s new Reform administration paused the second phase for assessment after hearing of businesses’ concerns about falling footfall, and trade, due to the disruption.
The council’s cabinet heard recently phase one work is going on and an existing delay means the time is being used for the re-assessment whereupon a revised second phase can begin.


As residents and businesses await more details, a new group - Brighouse Independent Shopkeepers (BRISK) has been set up.
BRISK says it has been a difficult seven months for businesses affected by the current work but, looking ahead, there is optimism.
William Marshall, Director of Reel Deal Gaming Centre, said phase one work has had a major impact with football and revenue “seriously down.”
But, he said, “the scheme when it is finished, it’s going to be wonderful.”


“The town will look fantastic and we’re not trying to oppose that in any shape or form but we feel that we just need some help and we want the council to give us some support.
“Immediately, we would like to see them try and consider to give us some free parking so we can promote the town, promote the free parking, and get people to come back into town as quickly as possible,” he said.
Manager of Websters Distinctive Furniture, Oliver Blackburn, said before the works started they were in favour of them and want Brighouse to be an improved, better place, and do want the investment.
“But we didn’t anticipate the downturn in footfall – people not coming who would usually come and being deterred away because of the walkways and the access to the town,” he said.
He urged the council to rethink plans to remove around 30 on-street parking spots in the town centre as part of the redevelopment.
“We want people to come into town – we know it is difficult at this time but we are supportive and we want to carry on being supportive.
“When the work is complete, hopefully then we can progress even further the town, the whole place will be improved for the better,” he said.
Gary Taylor, whose Edward & Co Hairdressers business falls into the area planned to be developed next, said lessons must be learned from the first stage of work, with better communication.
“Let’s learn from potentially what could have been avoided in the first phase to make it easier for businesses, to make it easier for shoppers.
“One of the things I am really passionate about is the council listens and for the shoppers, for example, while the development is going on, can we not have the first half hour of parking free?
“The parking charges have gone up 200 per cent – that’s a massive impact and we’ve had the disruption , so it’s been one thing after another for all the businesses.
“I am passionate about keeping Brighouse alive and welcoming all the shoppers saying ‘we are here, we are still open, we all need your support’ and we want to be here when Brighouse does look a lot, lot nicer,” he said.
Leader of Calderdale Council, Coun Dan Sutherland said the scheme was inherited from the previous Labour administration.