Calderdale Wind Farm: Next steps for contentious new Calderdale wind farm bid as number of turbines reduced
People are being asked to have their say on controversial plans for a new wind farm on Calderdale moorland which has had its planned turbine numbers reduced.
Consultation promotional leaflets which Calderdale householders have begun receiving have announced a timetable and the reduction in turbines for Calderdale Wind Farm Ltd’s (CWFL) proposals on Walshaw Moor, above Hebden Bridge.
When the company first announced last year it was preparing a scoping report to present to Calderdale Council, 65 turbines were planned - which would make it England’s biggest.
According to the consultation details released this week, the number proposed is now being reduced to 41 turbines, as well as a battery energy storage system plant.


The six-week – non-statutory – consultation closes on Tuesday, June 10, with the public invited to find out more and help shape the final proposal, says CWFL.
The current revised layout announced today also removes previously proposed solar panel elements, they say.
The Calderdale Energy Park has been designated as a Nationally Significant Infrastructure Project by the Secretary of State for Energy Security and Net Zero, Ed Miliband, because of its electricity generation capability, says the company.
This means that Calderdale Energy Park will require a Development Consent Order from the Secretary of State.
The first stage of consultation is a non-statutory consultation to gather initial public feedback on the proposals, says CWFL, which will then hold a formal statutory consultation on their updated plans later this year.
In person events people can attend have been arranged by CWFL at Hebden Bridge Town Hall on Tuesday, May 13, from 1.30pm to 7pm; at Oxenhope Community Centre on Saturday, May 17, from 12pm to 5pm; and at Trawden Forest Community Centre in Colne on Thursday, May 29, from 1.30pm to 7pm.
CWFL will also be holding an online webinar on Wednesday, May 21, between 6.30pm and 8pm. People can sign up to this by visiting the project website at www.calderdaleenergypark.co.uk, which also includes an online feedback form.
People can also contact the project team with questions or provide feedback via email at [email protected], or by phoning 01422 702506 between 9am and 5:30pm, Monday to Friday.
The proposals are opposed by a range of campaigners worried about the impact on peatland and natural habitats.
They are hoping the Government will listen to concerns about protecting peatland from wind farm development.
Campaign group Stronger Together to Stop Calderdale Wind Farm has launched a petition aiming to get 100,000 signatures to secure an MPs’ debate at https://petition.parliament.uk/petitions/701290
Calder Wind Farm Ltd argues that the Calderdale Energy Park “presents key opportunity to support Net Zero” and is a major opportunity to support the UK’s renewable energy transition and contribute to the Government’s Net Zero 2050 target.
The energy park would be capable of generating enough electricity to power the equivalent of approximately 250,000 homes and reduce national CO2 emissions by approximately 354,000 tonnes each year, they claim.
The non-statutory consultation leaflets posted out indicate a timeline of process with a Secretary of State decision anticipated in 2027.