This is when Huddersfield Station will close as Brighouse to be used as key road-rail interchange point

Huddersfield Station to close from next month with Brighouse used as a key road-rail interchange point to allow for works to take place.

Huddersfield Station will be closed following the last train service on Thursday, December 24 until Sunday, January 31, while extensive upgrades are completed as part of the Transpennine Route Upgrade (TRU).

During the closure, no trains will be able to run through Huddersfield station with diversionary routes and rail replacement buses in operation to keep customers on the move.

Brighouse station will be a key road-rail interchange point for customers travelling to and from Huddersfield during this period.

Brighouse Train Station.placeholder image
Brighouse Train Station.

When Huddersfield Station reopens on February 1, customers will be able to use the newly rebuilt and extended platforms 4, 5 and 6 for the first time.

As well as the longer platforms there will be new waiting areas and the station's historic roof canopy will have been restored.

placeholder image
Read More
Read more: 37 photos that will take you back to nights out in Halifax town centr...

Sophie Leishman, TRU Sponsor, said: "This closure will mark a major milestone for the Transpennine Route Upgrade, delivering significant improvements to Huddersfield station while laying the foundations for future benefits across the route.

Huddersfield Station improvement work.placeholder image
Huddersfield Station improvement work.

“When the station reopens, customers will see the benefits of new platforms and enhanced facilities, alongside major railway infrastructure improvements that will support future benefits for those travelling across the North.

“We are grateful to customers and local communities for their continued patience and support while we deliver these vital upgrades."

Carl Harland, TRU Customer Lead at Northern, said: “While extensive works are taking place at Huddersfield Station, we will once again be using the car park at Brighouse Station as a rail-road interchange to help keep customers on the move.

“We advise all customers to thoroughly check the details of their journey before they travel, as their journey may be subject to an amended timetable, a diversionary route, or may be replaced in part or whole by bus.

“We would like to thank our customers, especially those who travel through Huddersfield regularly, for their continued patience while these transformational works are undertaken at the Station.”

Some further enhancements at Huddersfield Station will continue from February onwards, including the completion of the historic tearoom restoration, the refurbishment of the platform 2 toilets and additional upgrades to customer facilities, while wider railway improvements across the TRU route continue to be delivered.