When next phase of Calderdale village flood scheme is due to start

The first phase of a Calderdale village flooding alleviation project – which has involved strengthening more than 500 metres of embankment – has now been completed.

And work on the second phase of plans for Copley should see the full business case for the project submitted by the end of the year, with work expected to start in the next financial year, 2026-27.

Work on the first phase of schemes for Copley began in spring 2024 and finally completed after dry weather had delayed grass seeding of the final embankment stretch at Old Rishworthians rugby club.

Once this new grass has been firmly established, the embankment will be opened to the public, Environment Agency (EA) officers told flood project partners.

Copley, Halifaxplaceholder image
Copley, Halifax

Phase one of the scheme better protects 229 properties in Copley village.

Work was split into three phases.

The Copley scheme’s second phase will see drainage work at Copley Cricket Club’s ground and a canal overflow project at the Calder and Hebble Navigation.

EA officers said: “Designs have been completed, modelling work is being internally reviewed, ground investigation is complete, and we hope to submit a Full Business Case along with a planning application by the end of 2025.

“The current plan is to commence construction next financial year.”