'We'll finish one set of roadworks before we start the next' council pledge ahead of more disruption for Halifax town centre
The next step in a massive overhaul of how we travel around Halifax town centre will not start until other work has finished, Calderdale Council is promising.
Despite orders being submitted to close several roads and temporarily change others to one-way at the bottom of the town centre from February 5, the council is pledging not to enforce these measures until work currently underway at the top of the town centre is done.
And it is launching two drop-in events where people can find out more about what is in store.
“We want to reassure people that construction in this area will not begin until construction work at the top of town is complete – planned for April 2026,” said Calderdale Council’s cabinet member for regeneration and transport, Coun Sarah Courtney.


"This is part of the phased approach which has been planned to minimise disruption as much as possible.
"We’ll make sure that the changes to traffic and travel will be promoted well ahead of work beginning to allow people to plan their routes in advance and ensure that diversion routes will be well signed.
“We’re also holding drop-in events for people to find out more about the works and hear more about the challenges of delivering this unprecedented programme of investment in our town centre.”
The Courier revealed at the end of last month how road closure and changes notices had been submitted and how, to allow the work to take place, several routes will be closed until next year.


The town centre has already endured many months of disruption since the huge revamp was launched in 2024.
As well as frustration from workers, residents and shoppers, there has been concern from traders who say they have seen a significant drop in footfall since the work started.
The council says the project, funded by the West Yorkshire Combined Authority, has been designed to “reduce journey times, make travel safer, improve public space and improve air quality, as well as deliver economic growth”.
The work it says is almost complete around the top of Halifax includes new road layouts, routes and junctions “to make all types of travel easier and safer”.


"The next phase will focus on the bottom of town, with upgrades including a better connection between Halifax Rail Station and the town centre through a new town gateway,” said a spokesperson for the council.
"There will be a new road, and new routes to improve traffic flow.”
Coun Courtney added: “We’re delivering change on a grand scale in Halifax town centre.
"So far, work has been focused around the top of the town, with improvements around Bull Green and surrounding areas.


"This was the most complex part of the project, with so many work areas and different junctions to navigate.
"As this difficult phase of construction work nears completion, we’re putting in place the processes to begin work on the next phase, with work focused on the area close to the rail station and Minster.”
The council says “all major routes will be kept open once work starts later in the spring”.
It says a diversion will guide traffic around the newly-open western route, and away from the Shaw Hill/South Parade route into the town centre.
Traffic will not be able to travel north on Church Street, from the junction at New Road/Prescott Street to the railway station.
According to the road orders, Charles Street, Square Road, Church Street and South Parade will be closed northbound until June 2, 2027.
The closures will be between Hunger Hill and King Street. Drivers will still be able to drive southbound.
The alternative route for northbound traffic will be via Skircoat Road, Portland Place, Commercial Street, Fountain Street, Barum Top, Bull Green, Cow Green, Broad Street, Northgate, and Winding Road.
Cripplegate/Lower Kirkgate will also be closed to vehicles northbound from the junction of Berry Lane to the junction of King Street.
The alternative route for northbound traffic will be via Skircoat Road, Portland Place, Commercial Street, Fountain Street, Barum Top, Bull Green, Cow Green, Broad Street, Northgate, Winding Road, and King Street. The route is expected to be closed until October 2027.
Blackedge will be temporarily one-way until October 2027.
Vehicles won’t be able to travel westbound from the junction of Square Road to the junction of Thomas Street.
The alternative route for westbound traffic will be via Horton Street. Eastbound access will be maintained.
Bank Bottom will be closed eastbound from the junction of Cripplegate to the junction of Southowram Bank until June 2027.
The alternative route for eastbound traffic will be via Skircoat Road, Portland Place, Commercial Street, Fountain Street, Barum Top, Bull Green, Cow Green, Broad Street, Orange Street, Burdock Way, New Bank, and Charlestown Road.
The drop-in information events will involve the contractor for the works, Galliford Try, and members of the council’s project team. These will take place in Albany Arcade in Halifax Borough Market on Thursday, 19 from 6pm to 8.30pm and Saturday, February 21 from 9am until 4pm.