First phase of £120m A629 scheme is complete - here's what is planned next

The first phase of the massive £120m A629 improvement scheme is now complete after 15 months.

Here we take a look back at the scheme, what has been done, why the work was delayed and when the next phase of the work will begin.

First phase of the 120m A629 project is now completeplaceholder image
First phase of the 120m A629 project is now complete
The Salterhebble phase of the A629 scheme began in August 2017. It was estimated that the project would take 52 weeks to complete.placeholder image
The Salterhebble phase of the A629 scheme began in August 2017. It was estimated that the project would take 52 weeks to complete.
As part of the project, 5000 tonnes of soil have been removed to widen the highway to four lanes.placeholder image
As part of the project, 5000 tonnes of soil have been removed to widen the highway to four lanes.
Two junctions have been remodelled and 6000 soil bags and seven million seeds have been used to help create a living wall.placeholder image
Two junctions have been remodelled and 6000 soil bags and seven million seeds have been used to help create a living wall.
Pedestrian and cycle lanes have also been included in a bid to make journeys more safer.placeholder image
Pedestrian and cycle lanes have also been included in a bid to make journeys more safer.